Relative Gantt in MS project

chartsmicrosoft-project

Is there a way to create a relative Gantt in MS project, that is a Gantt that doesn't have a defined start date, just amount of time required for each task?

Best Answer

Perhaps you didn't want to show specific dates, a generic 'duration' schedule? This is referred to as an Ordinal timescale in Primavera's schedule software. MS Project achieves this by change the timescale labels to show 'month 1', 'month 2', etc. -- then just hide any date columns and you have a generic schedule.