Hiding non-working time in MS Project

microsoft-projectproject-management

How can one hide the non working time in MS Project? I mean I want the calendar zone of the gant chart not to display weekends and holidays. Is this possible?

Best Answer

You cannot hide the display of Saturday and Sunday in the Gantt chart view. You can show a "5 day" week in the Calendar view.